Project Delivery Workflow

Productsarrow-up-right are the solutions we build for our customers, including Knack apps, AMANDA apps, custom software, and data systems. We improve and extend our products over time so that they deliver continuous value to Austin Transportation as business needs evolve.

Projectsarrow-up-right are time-boxed endeavors. They accomplish a singular goal and have a defined completion date. Examples include:

  • Recommending an off-the-shelf externally-supported solutionarrow-up-right

  • Delivering the first iteration (MVP) of a new DTS product

hashtag
Project Initiation

Oftentimes, our customers initiate a project by submitting a DTS service request that is notably large and/or important.

A DTS team member may also create a project when there is significant work to be done on an internal product—such as , , or .

In either case, we begin by verifying that all our DTS project prerequisites are met:

  • Dedicated product owner to support requirements gathering, user research, and user onboarding

  • Division Manager sponsor to champion the project at the executive level

  • A commitment from the customer to collaborate in DTS's iterative, user-centered development process

Then either or convert the existing issue to match the . Either way, make sure that the 'Project Index' label is on the issue so that an evaluation record for the project is added to the DTS Portal and it appears on the website.

circle-info

Don't worry about building out a robust project index before scoping the request. Just make sure the name and description (the first 1-2 sentences) are good and that it has all the right labels. You can comment out the rest of the template to fill out when you have more information.

Move the issue to the "Needs Scoping" Zenhub pipeline.

hashtag
Scoping

  • PM schedules an intake meeting. Ideally, this will include actual users as well as the workgroup manager.

  • Prepare .

  • Meet and take notes; photos/recording may also be helpful.

hashtag
Builder Huddle

  • PM sets up meeting with potential builders, e.g. Dev for a Vision Zero Viewer project, Apps for a ROW Portal project. If we aren't sure which route we'll go or the solution will require both, add to the to discuss.

  • Prepare a summary of request. Here's an ().

  • At the meeting, discuss the recommended approach and fill out the "Effort" section of the .

circle-info

Sometimes we realize that the request isn't actually project-sized during the intake meeting or the builder huddle. No worries, we had a good opportunity to learn more about our customers' work. Might make sense to organize this work as an , once the time comes.

hashtag
Product Sync

After assessing effort with the builders, it's time to assess value with the product team.

  • Add to for a "Refinement-week", i.e. the second Wednesday in a sprint. If feedback is needed sooner, or the project was initiated internally (like work on our technical infrastructure), bring it to instead.

  • As a group, fill out the "Value" section of the .

After the evaluation is complete, the Austinmobility.io script will pick them up and you will be able to see the project in relation to other projects in our backlog using the .

Move the index issue into the "Backlog" pipeline.

hashtag
Prioritization

hashtag

Google presentation used for Product Ops onboarding and TPW Executive communications.

hashtag
Working docs

hashtag
Activation

Once the time comes to work on the project:

  • Move the issue to the "In Progress" pipeline.

  • If you don't already have regular Sprint Reviews with the project's stakeholders, set up recurring meetings for the duration of the project so that you can demo work and get feedback.

  • Create a folder in the Projects/Products DTS Drive.

  • Convert the project index issue into an epic and assign future issues to the epic moving forward. Zenhub allows you to nest epics or assign issues to multiple epics, so feel free to use that functionality if you find it helpful.

  • Ensure that everyone who has stake in the project, from potentially impacted staff to interested executives, is aware the project is moving forward. Invite stakeholders to come to sprint reviews and/or participate in user research. Ask them who else should be included.

  • Optionally, hold a with your stakeholders.

hashtag
Delivery

  • Perform requirements gathering with users. We often begin with and store requirements either as for in-house applications or in a software comparison matrix for off-the-shelf solutions.

  • Document bugs, feature requests, and enhancements as Github issues. You may want to encourage your users to contribute using the .

circle-info

When you click the "New Issue" button in the upper righthand corner of most pages in Github, you'll find issue templates for bug reports, features, and enhancements. You have to scroll to the bottom of the page and click to the "Open a blank issue" link to get a plain issue. To skip all that, bookmark the and add it to your browser bar.

  • Work with the team lead—via Github comments or in a planning/refinement/sync meeting—to assign an to each issue. Zenhub's is also a fun way to estimate asynchronously.

  • Bring complex issues to Backlog Refinement ( | ) to discuss with builders. Break them up into smaller issues as necessary, document the agreed-upon approach, and align on an .

  • Prioritize work with stakeholders during Sprint Reviews.

hashtag
Completion

A project is considered complete when the minimum viable product—captured in the "Scope and Deliverables" section of the issue's project index—is delivered to users.

circle-info

For complex projects, you might consider making an "Onboarding and Stabilization" epic in the project to capture any critical bugs documentation needs that surface during roll out and keeping the project open until those issues are addressed.

  • Often, there are still issues in the backlog that are not actually must-haves. Remove the project label, remove them from the epic, and review them the next time you meet with stakeholders so they can prioritize those against any of their other ongoing requests.

  • Retire the project label by adding "[Archive]" to the "Description" field and update the hex code to #B8B8B7.

  • Write a final update as a comment on the index issue and close the issue.

  • By default, completed projects show on of the website, but you can apply the Archived Project label to prevent that. We like to curate this page to showcase our most compelling, impactful, and well-documented work.

Add notes/photos/recording to Github issue.

  • If necessary, update issue description to ensure it clearly summarizes request.

  • . Fill out the "Description" field and use the hex code #3D3D3D for "Color." Use this label for all issues moving forward so that they render on the projects' website page and are easy to surface on Zenhub/Github.
  • Fill out the rest of the project index including background, outcomes, timeline, etc. Add these headings to the issue:

  • If practical, versions of an application on a regular basis.

  • Perform usability testing to surface improvements to the user experience. Since we don't have dedicated user researchers at DTS, we love for its simplicity and depth of insight. we've done. It's handy to record sessions on Teams so that you can expand on your notes, embed screenshots/clips in issues, etc.

  • Building a major feature for an existing DTS projectarrow-up-right
    Refactoring a datasetarrow-up-right
    Delivering a complex maparrow-up-right
    updating Austinmobility.ioarrow-up-right
    a technical refactor of the Vision Zero Databasearrow-up-right
    migrating our CCTV image service from a local server to the cloudarrow-up-right
    create a new project index issuearrow-up-right
    project index templatearrow-up-right
    Intake Meeting Agendaarrow-up-right
    Dev/Product Sync agendaarrow-up-right
    example done as a presentation deckarrow-up-right
    templatearrow-up-right
    project evaluation in the DTS Portalarrow-up-right
    epic
    DTS Product Sync agendaarrow-up-right
    Dev + Product Syncarrow-up-right
    project evaluation in the DTS Portalarrow-up-right
    prioritization matrixarrow-up-right
    Project Prioritization Process as of 5/24arrow-up-right
    Project Prioritization workflowarrow-up-right
    DTS + OPM workflowarrow-up-right
    kick-off meetingarrow-up-right
    user interviewsarrow-up-right
    user storiesarrow-up-right
    DTS Service Requestarrow-up-right
    direct link to the blank issue formarrow-up-right
    estimatearrow-up-right
    Planning Pokerarrow-up-right
    Appsarrow-up-right
    Devarrow-up-right
    estimatearrow-up-right
    "Complete" tab on the “Projects" pagearrow-up-right
    ## Scope & Deliverables
    
    What are we delivering? What’s in scope, and what isn’t? Describe constraints you’re working with, e.g. “Can’t impact **\_**‘s workflow,” known roadblocks.
    
    ## Desired Outcomes
    
    Impact this project can have, success metrics
    
    ## Timebox
    
    How long should this take to build; optional section w/ caveats for more complex projects.
    
    ## References
    - Google Drive link 
    Create a Project: label in Githubarrow-up-right
    release
    think-aloud usability testingarrow-up-right
    Here are some think-aloud test plansarrow-up-right